APPROVE CHANGE ORDER AND BUDGET ADJUSTMENT TO COMPLETE ADDITIONAL WORK FOR THE STORM DRAIN REHABILITATION PROJECT, PHASE IV — approved 4-0
Council Meeting (Closed Session 4:00 PM - Cancelled), item 5, APPROVE CHANGE ORDER AND BUDGET ADJUSTMENT TO COMPLETE ADDITIONAL WORK FOR THE STORM DRAIN REHABILITATION PROJECT, PHASE IV was approved (4-0). [Minutes, p. 2]
The record
- Meeting
- Council Meeting (Closed Session 4:00 PM - Cancelled)
- Body
- City Council
- Item
- 5
- Request
- Request the City Council adopt Resolution No. 2026-158 authorizing (1) a change order with Sancon Technologies, Inc. in an amount of $688,588 to add rehabilitation of a 48” storm drain pipeline to the Storm Drain Rehabilitation, Phase IV Project (“Project”); and (2) a budget adjustment request for the change order.
- Staff recommendation
- approval
- Presented by
- Jason Christman
- Outcome
- approved
- Vote
- 4-0
- Moved by
- White
- Seconded by
- Fitzgerald
- Amount
- $688,588
- Case or file number
- 0910-20
From the document
Every field above was read from one of these passages.
5. APPROVE CHANGE ORDER AND BUDGET ADJUSTMENT TO COMPLETE ADDITIONAL WORK FOR THE STORM DRAIN REHABILITATION PROJECT, PHASE IV
Request the City Council adopt Resolution No. 2026-158 authorizing (1) a change order with Sancon Technologies, Inc. in an amount of $688,588 to add rehabilitation of a 48” storm drain pipeline to the Storm Drain Rehabilitation, Phase IV Project (“Project”); and (2) a budget adjustment request for the change order. (File Number 0910-20)
Staff Recommendation: Approval (Development Services Department: Kevin Snyder, Director
Presenter: Jason Christman, Interim City Engineer
Motion: White; Second: Fitzgerald; Approved: 4-0 (C. Garcia – Absent)