HALE AVENUE RESOURCE RECOVERY FACILITY (HARRF) DIGESTER CLEANING PROJECT: BID AWARD AND BUDGET ADJUSTMENT — approved 4-0

Council Meeting (Closed Session 4:00 PM - Cancelled), item 8, HALE AVENUE RESOURCE RECOVERY FACILITY (HARRF) DIGESTER CLEANING PROJECT: BID AWARD AND BUDGET ADJUSTMENT was approved (4-0). [Minutes, p. 2]

Machine-written from the record · Checked by an editor · Updated Nov 13, 2026

The Escondido City Council approved a $2,171,250 contract with Synagro-WWT, Inc. to clean the digesters at the Hale Avenue Resource Recovery Facility, along with a budget adjustment of $1,688,156.50.

The vote was 4-0, with C. Garcia absent. Council member White made the motion and Council member Fitzgerald seconded it.

The action was Resolution No. 2026-136. It lets the Mayor sign a Public Improvement Agreement with Synagro-WWT, Inc. for the Hale Avenue Resource Recovery Facility Digester Cleaning Project. The council approved it at its October 1, 2026 meeting. Staff from the Utilities Department, led by Daniel Peterson, Director of Utilities, recommended approval. Kyle Morgan, Assistant Director of Utilities, Wastewater, presented the item.

The minutes list this item under File Number 0600-10; A-3622.

The record

Meeting
Council Meeting (Closed Session 4:00 PM - Cancelled)
Body
City Council
Item
8
Request
Request the City Council adopt Resolution No. 2026-136 authorizing (1) the Mayor to execute a Public Improvement Agreement in the amount of $2,171,250 with Synagro-WWT, Inc. for the Hale Avenue Resource Recovery Facility (“HARRF”) Digester Cleaning Project (“Project”); and (2) a Budget Adjustment in the amount of $1,688,156.50.
Staff recommendation
approval
Presented by
Kyle Morgan
Outcome
approved
Vote
4-0
Moved by
White
Seconded by
Fitzgerald
Amount
$2,171,250
Case or file number
0600-10; A-3622

From the document

Every field above was read from one of these passages.

Motion: White; Second: Fitzgerald; Approved: 4-0 (C. Garcia – Absent)
Page 2
8. HALE AVENUE RESOURCE RECOVERY FACILITY (HARRF) DIGESTER CLEANING PROJECT: BID AWARD AND BUDGET ADJUSTMENT
Page 3
Request the City Council adopt Resolution No. 2026-136 authorizing (1) the Mayor to execute a Public Improvement Agreement in the amount of $2,171,250 with Synagro-WWT, Inc. for the Hale Avenue Resource Recovery Facility (“HARRF”) Digester Cleaning Project (“Project”); and (2) a Budget Adjustment in the amount of $1,688,156.50. (File Number 0600-10; A-3622)
Page 3
Staff Recommendation: Approval (Utilities Department: Daniel Peterson, Director of Utilities)
Page 3
Presenter: Kyle Morgan, Assistant Director of Utilities, Wastewater