Agenda item

REQUEST APPROVAL FOR CHANGE ORDER TWO AND AN ANTICIPATED THIRD CHANGE ORDER TO THE PUBLIC IMPROVEMENT AGREEMENT WITH PALM ENGINEERING CONSTRUCTION COMPANY, INC. FOR THE MOUNTAIN VIEW PARK PICKLEBALL COURTS PROJECT — approved 5-0

Council Meeting (Closed Session 4:00 PM), item 6, REQUEST APPROVAL FOR CHANGE ORDER TWO AND AN ANTICIPATED THIRD CHANGE ORDER TO THE PUBLIC IMPROVEMENT AGREEMENT WITH PALM ENGINEERING CONSTRUCTION COMPANY, INC. FOR THE MOUNTAIN VIEW PARK PICKLEBALL COURTS PROJECT was approved (5-0). [Minutes, p. 4]

Tier 3 · Human approved · Updated Sep 8, 2026

The Escondido City Council approved paying Palm Engineering Construction Company, Inc. an additional $131,340 to build a concrete patio with retaining walls and sidewalks at the Mountain View Park pickleball courts, and cleared the way for up to $45,000 more if the site needs maintenance access. The council voted 5-0, on a motion by White seconded by C. Garcia.

The patio is meant to serve as a gathering space and possibly as an area the city could rent out for events. The extra work was added to the existing construction agreement for the pickleball courts through what the city calls a change order, a written amendment to the contract the mayor signs on the city's behalf. The $45,000 is a ceiling rather than a bill: it covers a third change order the city expects it may need, and only if more money turns out to be required for getting maintenance access to the site.

City staff had recommended approval. The item came from the Development Services Department, headed by Director of Development Services Kevin Snyder, and was presented to the council by project manager Michael Tully.

Residents who want to look up the paperwork can search for Resolution No. 2026-130 or File Number 0910-20.

The record

Meeting
Council Meeting (Closed Session 4:00 PM)
Body
City Council
Item
6
Request
Request the City Council adopt Resolution No. 2026-130: (1) authorizing the Mayor to execute, on behalf of the City, change order number two to the Public Improvement Agreement with Palm Engineering Construction Company, Inc. for the installation of a concrete patio area with retaining walls and sidewalks as gathering space and potential rental event space area in the amount of $131,340; and (2) authorizing the Mayor to execute, on behalf of the City, a third change order to the Public Improvement Agreement with Palm Engineering Construction Company, Inc. in an maximum amount of $45,000 should additional funds be needed for maintenance access to the site.
Staff recommendation
approval
Presented by
Michael Tully, Project Manager
Outcome
approved
Vote
5-0
Moved by
White
Seconded by
C. Garcia
Amount
$131,340
Case or file number
0910-20

From the document

Every field above was read from one of these passages.

6. REQUEST APPROVAL FOR CHANGE ORDER TWO AND AN ANTICIPATED THIRD CHANGE ORDER TO THE PUBLIC IMPROVEMENT AGREEMENT WITH PALM ENGINEERING CONSTRUCTION COMPANY, INC. FOR THE MOUNTAIN VIEW PARK PICKLEBALL COURTS PROJECT Request the City Council adopt Resolution No. 2026-130: (1) authorizing the Mayor to execute, on behalf of the City, change order number two to the Public Improvement Agreement with Palm Engineering Construction Company, Inc. for the installation of a concrete patio area with retaining walls and sidewalks as gathering space and potential rental event space area in the amount of $131,340; and (2) authorizing the Mayor to execute, on behalf of the City, a third change order to the Public Improvement Agreement with Palm Engineering Construction Company, Inc. in an maximum amount of $45,000 should additional funds be needed for maintenance access to the site. (File Number 0910-20)
Page 4
Staff Recommendation: Approval (Development Services Department: Kevin Snyder, Director of Development Services) Presenter: Michael Tully, Project Manager
Page 4
Motion: White; Second: C. Garcia; Approved: 5-0
Page 4

Read the source document